Updated May 21, 2021

 

See below for a list of current projects that may impact vehicle and pedestrian travel.

 

Questions? Contact Matt Metzler at mmetzler@cityoflancasterpa.com or (717) 291-4777.

 

 

NORTH and SOUTH PRINCE STREET PAVING (PennDot/Alan Myers)

Contractors for Penndot have begun ADA ramp work.  Milling and Paving is scheduled to begin in early June. Milling, utility adjustments, leveling, paving, and line painting will follow.  This work will continue throughout the spring and summer.  Expect travel delays during this work.

 

 

LARGE DIAMETER TRANSMISSION MAIN, EAST HEMPFIELD TWP – WATER MAIN

Contractors for the City of Lancaster (Wexcon) continue a 24- to 30-month project to install a secondary, redundant large diameter transmission main from the City of Lancaster’s Oyster Point Reservoir in East Hempfield Township into the City of Lancaster. The project route is generally Hempland Road, Centerville Road, Old Tree Drive, Running Pump Road, Columbia Avenue, Eisenhower Boulevard, Wilson Drive, Marietta Avenue, Wheatland Avenue and Race Avenue. Work will continue on Wilson Ave. and Wheatland Ave. in Lancaster Twp over these next few weeks. Any questions on this project can be directed to Matt Metzler at (717) 291-4777.

 

 

Conestoga Pines Trail Bridge

This project involves the rehabilitation of an existing vehicular bridge for reuse as a pedestrian and bicyclist bridge over the Conestoga River to provide a connection between the Conestoga Pines Park and the Walnut Street Fishing Area within the City of Lancaster. The proposed structure is the existing Waterworks Bridge. The 204’ long, three-span, steel thru-girder bridge was originally constructed in 1912 and its center span was rebuilt in 1973 after a flooding event. The bridge is designed for combined pedestrian/bicycle use.  Activities include repairing/replacing deteriorated steel members and connections, installing concrete curb and bicycle railing, painting the structure, paving bridge deck and approaches, as well as other miscellaneous construction items.

 

 

CITY STREET IMPROVEMENT PROGRAM

This work will consist of ADA handicap ramps, milling, paving, and line painting.  Parking and driving lane restrictions will occur daily between 7:00AM and 5:00PM.  Please follow posted signs.  Please don’t hesitate to approach a worker or City employee with any questions or concerns.  Please contact the City of Lancaster at 717-291-4764.

The following streets will be impacted with milling/paving:

Prospect St – Manor St to Wabank St (End of June to Mid-July)

Hager St – Prince St to Queen St (End of June to Mid-July)

Franklin St – King St to Chestnut St (September to October)

Conestoga St – Queen St to Prince St (Mid-June to End of July)

Green St – Rockland St to Ann St (End of June to Mid-July)

Farnum St – Queen St to Water St (End of June to Mid-July)

Rockland St – Howard Ave to Green St and Dauphin St to Susquehanna St (End of June to Mid-July)

Strawberry St – Chesapeake St to Queen St (September to October)

Broad St – Chestnut St to Lehigh Ave (End of July)

Lemon St – Mulberry St to Lime St (Pending UGI work) (October)

 

Groffs Run Daylighting and Stream Restoration

This work involves the daylighting and restoration of a section of Groff’s Run, a stream channel that historically drained to the Conestoga River through the project area, but as the City grew over the past 100 years, has since had much of its baseflow cut off and directed to the City’s Combined Sewer System.  The project generally comprises grading of a defined stream channel and floodplain, installation of instream and floodplain grade control and habitat structures, bank stabilization, and related improvements (drainage, landscaping), and restoration of areas disturbed by construction operations.  The work also involves the relocation and protection of

existing utilities associated with the stream restoration project.  Please contact The City with any questions and concerns, 717-291-4764.

 

 

ADA CURB RAMP CONSTRUCTION – CITYWIDE

Work on ramps at various locations throughout the city has resumed for the 2021 construction season.  Contractors will replace approximately 30 ramps this year. Residents and motorists may encounter unexpected, short-term work zones because of this work. These are generally completed within about 2 weeks with weather cooperation. Please contact the Engineering Bureau at (717) 291-4764 with any specific questions or concerns on this work.

 

 

WATER AND WASTEWATER TRENCH RESTORATIONS

This work consists of the restoration of sewer and water utility trenches.  This work has begun and will last until fall.  You may encounter delays and road restrictions as part of this work.  Please call 717-291-4764 with any questions and concerns.

 

 

FIRE STATIONS REPLACEMENT, STATIONS 1 & 3

The Fire Station #1 on West King Street has a tentative completion date for the end of May 2021. Demolition/Construction is expected to begin on Fire Station #3 on East King Street in June.  Questions should be directed to Matt Metzler, Deputy Director of Public Works, at (717) 291-4777.

 

 

CITY OF LANCASTER GREEN INFRASTRUCTURE PROJECTS

James Street Mennonite – Improvements consists of stepped stormwater storage/infiltration trenches and related drainage structures. The project area, located in the James Street Mennonite Church parking lot, located off W James Street between N Mulberry Street and N Charlotte Street.

 

St. Joseph Street – Early June – Early September.  Project consists of vegetated high flow filter media curb extensions, vegetated curb extensions, and infiltration trenches. The project area is located on St. Joseph Street between Hershey Avenue and Prospect Street, extending on S Pearl Street up to Vine Street.

 

Alley 117NE – Project plans consist of stormwater storage/infiltration trenches and related drainage structures. The project area, located in Tobacco Alley, which spans from Franklin Street to Reservoir Street.

 

Highland Ave – Fall of 2021.  Green Plan Improvements consist of vegetated curb extensions, stormwater storage/infiltration trenches, and non-stormwater landscaped curb extensions. The project area located in Highland Ave between Greenwood Avenue and Furnace Street.

 

These projects are expected to begin in early June.  Each location will have its own construction schedule.  Please contact the Engineering Bureau if you have specific concerns about a location under construction at (717) 291-4764.

 

 

PPL NETWORK RELIABILITY PROJECT

PPL is replacing a network feeder on Prince St. which provides service to the downtown area.  This is a reliability project which will strengthen the underground network service.  The project is scheduled to begin on 3/9 and is expected to continue until June 2021.  The work on the second phase will be done in Fall 2021 and will be on Orange, Duke and King Streets.  Expect travel delays during this work.  Please contact the PPL at 1-800-DIAL-PPL or the Engineering Bureau at 717-291-4764 if you have questions.

 

 

PPL/DANELLA POLE REPLACEMENT PROJECT

PPL will be replacing telephone poles at various locations throughout the city. PPL is planning on approximately 30-40 locations per month with restorations following shortly after. This work is expected to continue until summer 2021. These are generally 1- or 2-day work areas. Please contact the PPL at 1-800-DIAL-PPL or the Engineering Bureau at 717-291-4764 if you have questions.

 

 

Verizon/Osmose Pole Project

Osmose Utilities will be working on reinforcing telephone poles at various locations throughout the city (generally located in the SE quadrant for the next week), these will be short term setups at each location with restoration to follow by ASG Inc. This work is expected to continue until summer 2021. These are generally 1- or 2-day work areas. Please contact Osmose at 770-632-6700 for pole related questions and Scott Magill/ASG Construction at 412-592-7284 for any restoration related questions.

 

 

UGI/SHILOH PAVING TRENCH RESTORATIONS

This work consists of the restoration of gas utility trenches.  This work has begun and will continue throughout the year as the crew’s progress. These are generally 1-2 day work areas, more involved locations will be listed below as we are made aware of their schedules. You may encounter delays and road restrictions as part of this work.  Please contact Brian Dollinger (UGI Restoration Supervisor) at (717) 255-1410 if you have questions.

 

The following streets will have mill/overlay operations in the coming weeks (should be 2-3 days as each location):

 

300 blk S. Ann St. (scheduled for the week of 5/24 weather permitting)

600 blk N. Cherry St. (scheduled for the week of 5/24 weather permitting)

 

 

UGI SIXTH ST MAIN AND SERVICE PROJECT

UGI/Miller Pipeline will continue working on gas main and services on Sixth St. from Ruby St. to S. West End Ave. Main/services are expected to be complete within 4 weeks with restorations following behind. Expect travel delays during this work. Please contact Rob Wholaver (UGI Senior Capital Supervisor) at 717-255-1484 if you have questions.

 

 

UGI LEMON ST MAIN AND SERVICE PROJECT

UGI/Kiely will continue working on replacing gas main and services on Lemon St. from Prince St. to Lime St. This work is expected to continue until June 2021. Expect travel delays during this work. Please contact Rob Wholaver (UGI Senior Capital Supervisor) at 717-255-1484 if you have questions.

100 Block E. Lemon St.- Services (Approx. 2 weeks)

Paving crews are scheduled to work on pavement restorations in the 000 blocks of East and West Lemon St. the week of 5/24/21. Expect travel delays during this work.

 

 

UGI NE POD PHASE 2 PROJECT

UGI/Kinsley Construction will continue working on main and service replacements related to their gas main replacement project in this area (see the image below for the project overview). This work is expected to continue until September 2021 with restorations following behind replacements. Expect travel delays during this work. Please contact Rob Wholaver (UGI Senior Capital Supervisor) at 717-255-1484 if you have questions.

Contractors will be working on the services at the following locations:

300 Block E Clay Street- Services (Approx. 3 weeks)

400 Block E Clay Street- Main and Services to follow (Approx. 4 weeks)

300 Block E Ross Street- Services (Approx. 3 week)

700 Block N Shippen Street- Main and Services to follow (Approx. 4 weeks)

400-500 blk E. Ross St. (Concrete sidewalk restorations, approximately 1 week)

 

 

COLONIAL MANOR WATER MAIN REPLACEMENT

A contractor for the City of Lancaster has started the water main replacement in the colonial Manor neighborhood. This project is due to the many water main breaks throughout this winter season. The water main will be replaced throughout the entire neighborhood along with paving and lawn restoration, over the next 2-3 months, ending in late summer. Please contact Jason Gore with any questions and concerns, 717-291-4773.

 

 

Eden Manor sewer interceptor replacement and conestoga pines trail improvements

A contractor for the City of Lancaster, Wexcon, Inc., has started preliminary work on the Eden Manor Sewer Interceptor and Conestoga Pines Trail Improvements project.  The work is generally described as the replacement of the existing sewer line that extends from the Eden Manor residential development at Princess Anne Drive downstream to its intersection with an existing sewer line prior to crossing under the Conestoga River.  Approximately three thousand two hundred (3,200) feet of sanitary sewer is to be replaced.  Approximately one thousand (1,000) feet of trail will be constructed from the Conestoga Pines Pool parking lot to the Conestoga Pines Trail Bridge through City of Lancaster property.   The project is anticipated to be completed in November of 2021. Please contact Bryan Harner with any questions or concerns at 717-293-5546.

 

 

maple grove pumping station and sewer interceptor expansion

The City’s Maple Grove Sewage Pumping Station on Meadow Creek Lane in Lancaster Township is to be upgraded/expanded by its General Contractor, Lobar, Inc.  This work is scheduled to be ongoing until the spring of 2022.  A contractor for the City of Lancaster, Wexcon, Inc., has started preliminary work on the sewer interceptor replacement up and downstream of the pumping station necessary for its expansion.  The expansion of the existing interceptor includes the replacement of approximately 3,600 feet of 24-inch to 30-inch sanitary sewer main; approximately 2,340 LF of 18-inch to 24-inch sanitary sewer main and approximately 300 LF of 24-inch to 24-in sanitary sewer main.  Work for this portion of the project will include temporary bypass pumping and maintenance of flows.  All work will take place within the public right of way or within existing easements on private property.  A general diagram/map showing the locations of these replacements is shown below and includes sewer replacements within Lancaster Township and the City of Lancaster.  This portion of the project is anticipated to be   completed in November of 2021. Please contact Bryan Harner with any questions or concerns at 717-293-5546.

 

 

Musser park renovation

The play area at Musser Park (N. Shippen & E. Marion Streets) will be closed effective March 15th to accommodate the replacement of the surfacing beneath the play equipment.  The existing surface and asphalt walkways will be removed, and a new system compromised of rubberized playground safety surface tiles will be installed.  Work is expected to take approximately 45 days, weather permitting.

 

 

South tank project

The South Tank is a 3-million-gallon finished water storage tank located adjacent to the Lancaster Community park at 1221 Millersville Pike in Lancaster Township. The project will serve the southwestern portion of the City of Lancaster’s water service area which includes Lancaster, Manor, and East Hempfield Townships and the Borough of Millersville.  The Project’s primary purpose is to increase the peak hourly demand pressures in the southwestern distribution system. The Tank will increase these peak demands by up to 40 psi in some areas and will provide an additional 5 – 10 psi increase in average pressures. This additional pressure will also increase capacities and resiliency of the system during emergencies such as a fire flow event.  Projected finish date for the steel construction is September of 2021, with a final completion date including painting and finishing of September of 2022.

 

 

Millersville pike water transmission main replacement

The Millersville Pike 16” Transmission main project will replace approximately 7,500 LF of aging 8” main with new 16” ductile iron pipe from the intersection of Millersville Pike and Charles Road in Lancaster Township, west to the intersection of Millersville Pike and Millersville Road in Millersville Borough. The project also includes full lane width milling and overlay on the effected lanes along the proposed replacement route.  The new transmission main will connect to the City’s South Tank Project, now under construction adjacent to the Lancaster Community Park at 1221 Millersville Pike and slated to be in service by September of 2022, and the ongoing large diameter transmission main project. This project will increase the available capacity and resiliency of the infrastructure in the southwestern portion of the City’s distribution system by increasing peak hourly demand pressures, enhancing water quality, and providing increase capacity for emergency situations.  The project is projected to begin in April and be completed in December of 2021.

 

 

Strawberry Street Water main replacement

Replacing aging 12” water main on E. Strawberry Street from the intersection of Juniata Street to S. Queen Street with a 12” Ductile iron water main. This project will include trenching for the water main replacement along with paving and sidewalk restoration. Daily street closures and parking restrictions will be in place to allow access for this construction project.

 

 

LPA CHRISTIAN ST. PARKING GARAGE AND LIBRARY PROJECT

This project began in September 2019 and is tentatively scheduled to be completed in October 2021. Expect lane shifts and restrictions on the 100 block of N. Queen St. until project completion. This project is scheduled to get several wide loads delivered daily starting approximately 5/24/21 until mid-July, these escorted wide loads will use N. Duke St., E. Orange St. and N. Queen St. which may cause very brief delays while the trucks make their turns. Questions should be directed to Sammy Ben-Nasr, Project Manager for Benchmark Construction at 717-626-9559.

 

 

LGH EMERGENCY DEPARTMENT EXPANSION PROJECT

This project began in Fall 2020 and is tentatively scheduled to be completed in Spring 2024. Expect lane shifts and restrictions on the 500 blocks of N. Lime and N. Duke Streets. E. Frederick St. will have the eastbound lane closed with intermittent weekend closures westbound between Lime and Cherry Streets, this work closure is expected to be in effect the following dates: April 2021-Late August 2021 & October 2021. Please follow the posted detour. Questions should be directed to Grant Wilcox, Project Manager for Benchmark Construction or Matthew Morimoto, Assistant Project Manager at 717-626-9559.

Frederick St. will be closed in both directions Saturday May 22nd west bound will be reopened to traffic Saturday afternoon. Please follow the posted detour during this closure.

PARKING INFO

We understand that residential parking can get tight near construction areas. Click here for a map of parking options. Streets not highlighted in red or blue are not restricted by meters or permits, and are available for parking on a first come, first served basis.